Winnetka Campus Facilities Project

News and Updates

  • Construction Update: Week of January 2, 2017
    Despite the frigid temperatures, workers continued to erect steel to complete the superstructure on the eastern half of the Phase 2 addition.  Next week the crane will be removed from the lower level and will move to the west of the addition in order to complete the two remaining steel sequences that are adjacent to Woodland Avenue.  Behind the white tarps, crews continue to pour concrete as metal decks become available.  Mechanical, electrical and plumbing work has already begun following the concrete pours, and the spray fireproofing process is expected to start over the next few weeks.

Construction videos

Steelwork